sandy wrote:
Jenny takes 3 hours to sand a picnic table; Laila can do the same job in \(\frac{1}{2}\) hour. Working together at their respective constant rates, Jenny and Laila can sand a picnic table in how many hours?
(A) \(\frac{1}{6}\)
(B) \(\frac{2}{9}\)
(C) \(\frac{1}{3}\)
(D) \(\frac{3}{7}\)
(E) \(\frac{5}{6}\)
Part of 1 hour work by Jenny = 1/3
Part of 1 hour work by Laila = 1 / 1/2 = 2.
Now part of 1 hour work by both = 1/3 + 2 = 7/3.
Now time inversely prop to work =? 3/7.