GRE Work/Rate Problems - Tips and Tricks you must know with examples
This is part of our
GRE Math Essentials project & GRE Math Essentials - A most comprehensive handout!!! that are the best complement to our
GRE Math Book. It provides a cutting-edge, in-depth overview of all the math concepts from basic to mid-upper levels. The book still remains our hallmark: from basic to the most advanced GRE math concepts tested during the exam. Moreover, the following chapters will give you many tips, tricks, and shortcuts to make your quant preparation more robust and solid.
1. If a man can do a piece of work in N days (or hours or any other unit of time), then the work done by him in one day will be \(\frac{1}{N}\) of the total work.
1. If A and B together finish a piece of work in 10 days & B alone can finish it in 20 days. In how many days can A alone finish the work ?
Sol. Let X and Y be the number of days required by A and B respectively. ⇒ By the standard formula, \(\frac{XY}{(X + Y)} = 10\) & \(Y = 20 ⇒ \frac{X \times 20 }{(X + 20)} = 10\) or X = 20 days
2. If A is twice as good a workman as B, then A will take half the time B takes to finish a piece of work.
2. Four men working together all day, can finish a piece of work in 11 days; but two of them having other engagements can work only one half–time and quarter time respectively. How long will it take them to complete the work ?
Sol. Each man will take 11 x 4 = 44 days to complete the work. If one man works half day/day he will take 44 x 2 = 88 days to finish the work. Similarly, a man working quarter \(\frac{day}{day}\) will take 44 x 4 = 176 days to finish the work. When these work together they will require \(\frac{1 }{\left[ \begin{array}{cc|r} (\frac{1}{44}) + (\frac{1}{44}) + (\frac{1}{88}) + (\frac{1}{176}) \end{array} \right] }= 16\) days.
3. If A and B can do a piece of work in X & Y days respectively while working alone, they will together take \(\frac{XY }{ (X + Y)}\) days to complete it.
3. 20 men can complete a piece of work in 10 days, but after every 4 days 5 men are called off, in what time will the work be finished ?
Total work = 20 x 10 = 200 monday
1. First 4 days' work = 20 x 4 = 80 md
2. Next 4 days' work = 15 x 4 = 60 md
3. Next 4 days' work = 10 x 4 = 40 md
4. Next 4 days' work = 5 x 4 = 20
\(Σ = 200\) md
Hence, days reqd = 4 + 4 + 4 + 4 = 16
4. If A, B, C can do a piece of work in X, Y, Z days respectively while working alone, they will together take \(\frac{XYZ }{ [XY + YZ + ZX]}\) days to finish it.
4. A vessel can be filled by one pipe A in 10 minutes, by a second pipe B in 15 minutes. It can be emptied by a waste pipe C in 9 minutes. In what time will the vessel be filled if all the three were turned on at once ?
Sol. We will follow exactly the same method as in time & work. The part of a vessel filled in 1 minute when all three are on \(= \frac{1}{10} + \frac{1}{15} – \frac{1}{9} = \frac{1}{18} ⇒\) Total vessel will be filled in 18 minutes
5. If an inlet pipe can fill a cistern in X hours, the part filled in 1 hour = \(\frac{1}{X}\)
5. Three pipes A, B and C can fill a cistern in 15, 20 and 30 min resp. They were all turned on at the same time. After 5 minutes the first two pipes were turned off. In what time will the cistern be filled ?
Sol. A, B and C can fill \((\frac{1}{15} + \frac{1}{20} + \frac{1}{30})\) or \(\frac{3}{20}\) of the cistern in 1 minute ⇒ A, B and C filled \((\frac{3}{20} x 5)\) or \(\frac{3}{4}\) of the cistern in 5 min. Now A and B are turned off \(⇒ (1 – \frac{3}{4})\) or \(\frac{1}{4}\) of the cistern wil be filled by C ⇒ C will fill \(\frac{1}{4}\) of the cistern in \((30 \times \frac{1}{4})\) or 7.5 minutes ⇒ The cistern will be filled in 7.5 + 5 or 12.5 min
6. If an inlet pipe can fill a tank in X hours and an outlet pipe empties the full tank in Y hours, then the net part filled in 1 hour when both the pipes are opened \(= (\frac{1}{X}) – (\frac{1}{Y}) ⇒\) In 1 hour, the part filled (or emptied) \(= \frac{1}{X }– \frac{1}{Y} ⇒ \) Time required to fill or empty the tank \(= \frac{XY }{ (X \sim Y)}\) hours. \(X \sim Y\) indicates \([X – Y]\) or \([Y – X]\), whichever is positive).
6. A cistern can be filled by two taps A and B in 12 minutes and 14 minutes respectively and can be emptied by a third in 8 minutes. If all the taps are turned on at the same moment, what part of the cistern will remain unfilled at the end of 7 minutes ?
Sol. We have \((\frac{7}{12}) + (\frac{7}{14}) – \frac{7}{8} = \frac{5}{24}\) part filled in 7 minutes. Hence \(1 – \frac{5}{24} = \frac{19}{24}\) th of the tank is unfilled.