Retired Moderator
Joined: 07 Jun 2014
Posts: 4812
Given Kudos: 0
WE:Business Development (Energy and Utilities)
Re: Noah’s contracting company builds road at a rate of 1 mile
[#permalink]
29 Dec 2017, 16:40
Explanation
Use the Rate Pie to organize your work. For the first 5 weeks, Noah’s company builds 1 mile per week. Therefore, they build 5 miles of road before the start of the rainy season. Once rainy season begins, they have 6 miles of road left to build. This number is the “work,” and goes in the top of the rate pie.
The rate, \(\frac{1}{2}\) miles per week, goes in the lower left segment of the rate pie. Divide 6 by , and you’ll get the total amount of time, or 12 weeks, at that rate.
Therefore, it will take a total of 17 weeks for Noah’s company to build the road.