Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.
Customized for You
we will pick new questions that match your level based on your Timer History
Track Your Progress
every week, we’ll send you an estimated GRE score based on your performance
Practice Pays
we will pick new questions that match your level based on your Timer History
Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.
Thank you for using the timer!
We noticed you are actually not timing your practice. Click the START button first next time you use the timer.
There are many benefits to timing your practice, including:
Your score will improve and your results will be more realistic
Is there something wrong with our timer?Let us know!
A can complete a project in 20 days and B can complete the same projec
[#permalink]
20 Sep 2021, 04:57
Expert Reply
2
Bookmarks
00:00
A
B
C
D
E
Question Stats:
52% (02:10) correct
47% (02:46) wrong based on 19 sessions
HideShow
timer Statistics
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
Re: A can complete a project in 20 days and B can complete the same projec
[#permalink]
21 Sep 2021, 06:30
1
Let T be the total number of days to complete the project. A can do 120 of work in one day and B can do 130 in one day and to gather they can for120+130=112 of the work.
So if A quit 10 days before the project is over, then T-10 days both worked and 10 days B alone worked to complete 1 task. 1=(T−10)12+1030 Solving to T, will be T = 18 days. Answer is A) 18