Re: A can complete a project in 20 days and B can complete the same projec
[#permalink]
21 Sep 2021, 06:30
Let T be the total number of days to complete the project.
A can do 120 of work in one day and B can do 130 in one day and to gather they can for120+130=112 of the work.
So if A quit 10 days before the project is over, then T-10 days both worked and 10 days B alone worked to complete 1 task.
1=(T−10)12+1030
Solving to T, will be T = 18 days.
Answer is A) 18