bellatrix wrote:
Working alone at its constant rate, machine K took 3 hrs to produce 1/4 of the units produced last Friday. Then machine M started working and the two machines working simultaneously at their respective constant rates took 6 hrs to produce the rest of the units produced last Friday. How many hours would it have taken machine M working alone at its constant rate to produce all of the units produced last Friday?
A) 8
B) 12
C) 16
D) 24
E) 30
Let's
assign a nice value to the TOTAL number of units produced on Friday.
We want a number that works well with the given numbers in the question (1/4 and 6)
So let's say a TOTAL of
24 units were produced
Working alone at its constant rate, machine K took 3 hours to produce 1/4 of the units produced last Friday. 1/4 of
24 = 6
In other words, machine K took 3 hours to produce 6 units
Rate = output/time = 6/3 = 2
So, machine K produces 2 units PER HOUR
Then machine M started working and the two machines, working simultaneously at their respective constant rates, took 6 hours to produce the rest of the units produced last Friday.24 - 6 =
18So, when machine M starts helping, the two machines have
18 units to produce
Rate = output/time =
18/
6 = 3
So, the COMBINED rate of the two machines is 3 units PER HOUR
We already know that machine K produces 2 units PER HOUR
3 - 2 =
1, so machine M produces
1 unit PER HOUR
How many hours would it have taken machine M, working alone at its constant rate, to produce all of the units produced last Friday?Time = output/rate =
24/
1 = 24
Answer: D
Cheers,
Brent