Last visit was: 27 Apr 2024, 06:10 It is currently 27 Apr 2024, 06:10

Close

GRE Prep Club Daily Prep

Thank you for using the timer - this advanced tool can estimate your performance and suggest more practice questions. We have subscribed you to Daily Prep Questions via email.

Customized
for You

we will pick new questions that match your level based on your Timer History

Track
Your Progress

every week, we’ll send you an estimated GRE score based on your performance

Practice
Pays

we will pick new questions that match your level based on your Timer History

Not interested in getting valuable practice questions and articles delivered to your email? No problem, unsubscribe here.

Close

Request Expert Reply

Confirm Cancel
Verbal Expert
Joined: 18 Apr 2015
Posts: 28658
Own Kudos [?]: 33139 [1]
Given Kudos: 25178
Send PM
avatar
Manager
Manager
Joined: 23 Jan 2016
Posts: 133
Own Kudos [?]: 209 [0]
Given Kudos: 0
Send PM
avatar
Intern
Intern
Joined: 12 Jul 2016
Posts: 8
Own Kudos [?]: 8 [4]
Given Kudos: 0
Send PM
Retired Moderator
Joined: 10 Apr 2015
Posts: 6218
Own Kudos [?]: 11690 [0]
Given Kudos: 136
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
1
Carcass wrote:
If it takes three days for 10 workers to finish building one house, how many days will it take 15 workers to finish four houses?

\(Days =\)

Show: :: OA
8


Another approach for questions like this is to assign a nice value to the job

Given: it takes three days for 10 workers to finish building one house
A nice number that works well with the numbers 3 and 10 is 30 (30 is the least common multiple of 3 and 10)
So, let's say one house has 30 rooms.
In other words, building ONE house requires the workers to build 30 rooms.

If 10 workers can build 30 rooms (aka one house) in 3 days, then in 1 day, the 10 workers can build 10 rooms.
If 10 workers can build 10 rooms in ONE DAY, then 1 worker can build 1 room in ONE DAY

How many days will it take 15 workers to finish four houses?
Our goal is to build 4 houses, which is the same as building 120 ROOMS
If 1 worker can build 1 room per day, then 15 workers can build a total of 15 rooms per day.
So, the number of days to build 120 ROOMS = 120/15 = 8 days

Answer: 8
User avatar
Manager
Manager
Joined: 19 Nov 2018
Posts: 102
Own Kudos [?]: 157 [2]
Given Kudos: 0
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
1
1
Bookmarks
I just used dimensional analysis (converting values using multiplication and cancelling of units).
Attachments

daum_equation_1565818310282.png
daum_equation_1565818310282.png [ 130.81 KiB | Viewed 12193 times ]

avatar
Manager
Manager
Joined: 08 Dec 2019
Posts: 51
Own Kudos [?]: 21 [0]
Given Kudos: 0
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
This is a very complicated question. I would elevate it to HARD difficulty. It's certainly not a medium question by any means. Takes multiple leaps of logic to figure this out. Change the difficulty, please.
Retired Moderator
Joined: 10 Apr 2015
Posts: 6218
Own Kudos [?]: 11690 [0]
Given Kudos: 136
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
Libra wrote:
This is a very complicated question. I would elevate it to HARD difficulty. It's certainly not a medium question by any means. Takes multiple leaps of logic to figure this out. Change the difficulty, please.


84% success rate ≠ HARD
avatar
Manager
Manager
Joined: 08 Dec 2019
Posts: 51
Own Kudos [?]: 21 [0]
Given Kudos: 0
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
GreenlightTestPrep wrote:
Libra wrote:
This is a very complicated question. I would elevate it to HARD difficulty. It's certainly not a medium question by any means. Takes multiple leaps of logic to figure this out. Change the difficulty, please.


84% success rate ≠ HARD


Ok, NOW I got it, and I didn't even use any of your explanations above because I honestly couldn't understand them. Here it goes, and I set up proportions:

10 workers to build one house in 3 days. Work = rate x time. 1 house = r(3 days). So the rate for 10 workers is 1 house every 3 days (r = 1/3). Then set up the proportion:

Workers/rate = workers/rate. 10 workers / (1/3) = 15 workers / (rate). Solve for the rate to get 1/2. So in other words, 15 workers can build 1 house in 2 days. Now we can answer the question "how many days will it take 15 workers to finish four houses?" If 1 house takes 2 days for 15 workers, then 4 houses take 8 days. bingo.

It's lovely when I can finally see it and provide a more streamlined explanation than the ones offered above. I never cease to amaze myself!
avatar
Intern
Intern
Joined: 19 May 2020
Posts: 6
Own Kudos [?]: 10 [0]
Given Kudos: 0
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
1
Carcass wrote:
If it takes three days for 10 workers to finish building one house, how many days will it take 15 workers to finish four houses?

\(Days =\)

Show: :: OA
8


for 10 workers 3 days to complete 1 house.
then, for 1 workers 3*10 =30 days to complete 1 house.
now ,if 1 workers can finish 1 house in 30 days,
then for 1 workers to finish 4 house tooks 4*30=120 days
so far, 1 workers 4 house 120 days ,
then 15 workers 4 house 120/15=8 days. :) :)
Retired Moderator
Joined: 10 Apr 2015
Posts: 6218
Own Kudos [?]: 11690 [1]
Given Kudos: 136
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
1
Bookmarks
Carcass wrote:
If it takes three days for 10 workers to finish building one house, how many days will it take 15 workers to finish four houses?

\(Days =\)

Show: :: OA
8

A student asked me to solve this in a different way, so here goes:

Given: It takes 3 days for 10 workers to finish building one house
Rate = output/time = 1/3
So, the 10 workers (combined) complete 1/3 of a house in one day.
This means ONE worker can complete 1/30 of a house in one day.
In other words, EACH worker's rate is 1/30 of a house per day.

How many days will it take 15 workers to finish four houses?
If EACH worker's rate is 1/30 of a house per day, then the combined rate of 15 workers = (1/30)(15) = 1/2
This means the TEAM of 15 workers has a combined rate of 1/2 houses per day.

Time = output/rate = 4/(1/2) = 8 days.
Manager
Manager
Joined: 10 Feb 2023
Posts: 76
Own Kudos [?]: 13 [0]
Given Kudos: 172
Send PM
Re: QOTD #3 If it takes three days for 10 workers to finish bu [#permalink]
Thanks Brent GreenlightTestPrep
Prep Club for GRE Bot
[#permalink]
Moderators:
Moderator
1085 posts
GRE Instructor
218 posts

Powered by phpBB © phpBB Group | Emoji artwork provided by EmojiOne